The current project schedule calls for the completion of the Precise Plan and associated EIR in no more than 18 months, which means adoption hearings are planned for December of 2014. The following are the primary phases of work for the project.

Process Schedule

Key Project Milestones:
  • Existing Conditions Reports: September 2013
  • Plan Alternatives Briefing Book: November 2013
  • 1st Public Workshop (review of plan alternatives): January 2014
  • EIR Notice of Preparation: January 2014
  • Public Draft Precise Plan: June 2014
  • Public Draft EIR: July 2014
  • Adoption: End of 2014